M&E Contractor Preliminaries Calculator 2025/26
Estimate mechanical and electrical contractor preliminaries as a percentage of M&E package value. Preliminaries cover site management, plant, welfare facilities, insurances and other on-cost items that are included in the contract price but not directly attributable to measured work.
Key Inputs
- M&E package value (£)
- Project duration (months)
- Project type: new build, fit-out, or refurbishment
- Site complexity: simple, standard, or complex (restricted access, live environment)
What You'll Get
- Estimated preliminaries as a percentage of M&E package value
- Preliminaries cost (£)
- Time-related vs fixed cost split
- Key items included and excluded from the estimate
Important Notes — 2025/26 Rates & Caveats
Typical UK M&E contractor preliminaries 2025/26: 8-15% of M&E package value for standard projects; 12-20% for complex, restricted access or live-environment projects. Key components: site management (contracts manager, site engineer — largest cost); welfare facilities (cabins, toilets, drying rooms); small plant and tools; insurances (CAR, PL, EL); temporary works; health and safety compliance; commissioning preparation. Preliminaries increase as a percentage for shorter-duration projects due to fixed mobilisation costs. Review preliminary items carefully in tenders — they are often a source of negotiation.
Frequently Asked Questions
What are contractor preliminaries?
Contractor preliminaries (or 'prelims') are the general costs of running the site that are not directly attributable to a specific measured work item. They include: site management staff, site huts and welfare facilities, small tools and plant, site fencing and hoarding, insurances, temporary services, health and safety measures, and project-specific requirements. Prelims are priced separately from measured work in a bill of quantities or schedule of rates. On M&E packages, prelims typically represent 8-15% of the package value.
How do M&E prelims differ from main contractor prelims?
Main contractor prelims cover the whole site and are typically 10-20% of the overall contract value. M&E sub-contractor prelims cover only the M&E team's site costs and are typically 8-15% of the M&E package. On a project procured under a main contract, the M&E contractor may benefit from main contractor site facilities (welfare, craneage) in which case M&E prelims will be lower. On design-and-build or specialist M&E contracts without a main contractor, M&E prelims will be higher as the M&E contractor must provide all site facilities.
What is the difference between fixed and time-related preliminaries?
Fixed preliminaries are one-off costs that don't change with project duration — mobilisation, demobilisation, initial site set-up, and specific method-related items. Time-related preliminaries vary with the project duration — site management salaries, welfare cabin hire, security, and similar running costs. When a project is extended, only time-related prelims change. Understanding the split is important for negotiating extensions of time claims and loss and expense — contractors are only entitled to time-related prelims for project overruns caused by employer-risk events.
Related Calculators
Use the interactive M&E Contractor Preliminaries Calculator
Run real numbers instantly — free, no sign-up required.
Go to Construction & Professional Calculators