Skip to main content

M&E Contractor Preliminaries Calculator 2025/26

Estimate mechanical and electrical contractor preliminaries as a percentage of M&E package value. Preliminaries cover site management, plant, welfare facilities, insurances and other on-cost items that are included in the contract price but not directly attributable to measured work.

Key Inputs

  • M&E package value (£)
  • Project duration (months)
  • Project type: new build, fit-out, or refurbishment
  • Site complexity: simple, standard, or complex (restricted access, live environment)

What You'll Get

  • Estimated preliminaries as a percentage of M&E package value
  • Preliminaries cost (£)
  • Time-related vs fixed cost split
  • Key items included and excluded from the estimate

Important Notes — 2025/26 Rates & Caveats

Typical UK M&E contractor preliminaries 2025/26: 8-15% of M&E package value for standard projects; 12-20% for complex, restricted access or live-environment projects. Key components: site management (contracts manager, site engineer — largest cost); welfare facilities (cabins, toilets, drying rooms); small plant and tools; insurances (CAR, PL, EL); temporary works; health and safety compliance; commissioning preparation. Preliminaries increase as a percentage for shorter-duration projects due to fixed mobilisation costs. Review preliminary items carefully in tenders — they are often a source of negotiation.

Frequently Asked Questions

What are contractor preliminaries?

Contractor preliminaries (or 'prelims') are the general costs of running the site that are not directly attributable to a specific measured work item. They include: site management staff, site huts and welfare facilities, small tools and plant, site fencing and hoarding, insurances, temporary services, health and safety measures, and project-specific requirements. Prelims are priced separately from measured work in a bill of quantities or schedule of rates. On M&E packages, prelims typically represent 8-15% of the package value.

How do M&E prelims differ from main contractor prelims?

Main contractor prelims cover the whole site and are typically 10-20% of the overall contract value. M&E sub-contractor prelims cover only the M&E team's site costs and are typically 8-15% of the M&E package. On a project procured under a main contract, the M&E contractor may benefit from main contractor site facilities (welfare, craneage) in which case M&E prelims will be lower. On design-and-build or specialist M&E contracts without a main contractor, M&E prelims will be higher as the M&E contractor must provide all site facilities.

What is the difference between fixed and time-related preliminaries?

Fixed preliminaries are one-off costs that don't change with project duration — mobilisation, demobilisation, initial site set-up, and specific method-related items. Time-related preliminaries vary with the project duration — site management salaries, welfare cabin hire, security, and similar running costs. When a project is extended, only time-related prelims change. Understanding the split is important for negotiating extensions of time claims and loss and expense — contractors are only entitled to time-related prelims for project overruns caused by employer-risk events.

Related Calculators

Use the interactive M&E Contractor Preliminaries Calculator

Run real numbers instantly — free, no sign-up required.

Go to Construction & Professional Calculators